Route 28 Lane Restrictions this Weekend in Allegheny County

​Pittsburgh, PA – PennDOT District 11 is announcing paving operations on Route 28 in East Deer, Fawn, and Harrison townships and Tarentum Borough, Allegheny County, will occur Friday, September 7 through Monday, September 10 weather permitting.

Paving operations requiring a single-lane restriction on Route 28 in each direction between the Natrona Heights (Exit 15) and Freeport/Millerstown (Exit 16) interchanges will occur according to the following schedule:

Southbound – 9 a.m. Friday morning continuously through 5 a.m. Monday morning

Northbound – 7 p.m. Friday night continuously through 2 p.m. Monday afternoon

The overall $34.34 million project includes concrete patching, an asphalt overlay, bridge preservation work, drainage and guiderail improvements, installation of a new automatic bridge de-icing system, lighting upgrades, and other miscellaneous construction activities. The project runs between Butler County and the structures spanning Bailies Run Road in East Deer Township.

Lindy Paving is the prime contractor.